St Lawrence & Durham Construction Weekly Schedule Update - JUNE 2 TO JUNE 6

St Lawrence & Durham Construction Weekly Schedule Update  - JUNE 2 TO JUNE 6

General Construction (Monday – Friday)

  • St. Lawrence East – Phase 3A: Gream Street working easterly

  • Durham Street North: Rock breaking, sanitary sewer

  • St. Lawrence East – Phase 2A / 3A: Wellington intersection working easterly


Curbside Construction (SUB)

Monday – Tuesday

  • St. Lawrence East – Phase 2B / 2A: Concrete curb & gutter

Wednesday – Friday

  • St. Lawrence East – Phase 2B / 2A: Sidewalks

Tuesday – Friday

  • St. Lawrence East – Phase 2A / 2B: Sidewalk prep, boulevard prep