St Lawrence & Durham Construction Weekly Schedule Update - MAY 20 TO MAY 23, 2025

Monday – Friday

-              Rock Breaking; Durham Street North (Sanitary Lateral investigation, Tuesday 8am)

-              St Lawrence East - Phase 2B, working Easterly 

-              Planning to have Phase 2B underground infrastructure completed by end of week

Monday – Friday

-              St Lawrence East – Phase 2A, working easterly

-              Cross Culvert (Elliptical pipe) / STM MH 5 completed Tuesday

-              Planning to have Phase 2A underground infrastructure completed by end of week