St Lawrence & Durham Construction Weekly Schedule Update - MAY 20 TO MAY 23, 2025
Monday – Friday
- Rock Breaking; Durham Street North (Sanitary Lateral investigation, Tuesday 8am)
- St Lawrence East - Phase 2B, working Easterly
- Planning to have Phase 2B underground infrastructure completed by end of week
Monday – Friday
- St Lawrence East – Phase 2A, working easterly
- Cross Culvert (Elliptical pipe) / STM MH 5 completed Tuesday
- Planning to have Phase 2A underground infrastructure completed by end of week