St Lawrence Street and Durham Street Reconstruction Weekly Update ( Week of May 26 - May 30th)

Weekly Updates for the Week of May 26 - May 30th
Monday – Friday
- Rock Breaking; Durham Street North
- Sanitary Sewer Install, Durham Street North
- St Lawrence East - Phase 2B; Sidewalk Removals, Watermain Testing, Prep for new Curb & Sidewalk
Monday / Tuesday
- Asphalt Removal (Pulverize); St Lawrence East – Wellington to Concession
- St Lawrence East – Phase 2A, Wellington Intersection
Wednesday – Friday
- Temporary Water service connections; St Lawrence East – Phase 3A / 3B (Wellington to Concession