St Lawrence Street and Durham Street Reconstruction Weekly Update ( Week of May 26 - May 30th)

St Lawrence Street and Durham Street Reconstruction Weekly Update ( Week of May 26 - May 30th)

Weekly Updates for the Week of May 26 - May 30th

Monday – Friday

  • Rock Breaking; Durham Street North
  • Sanitary Sewer Install, Durham Street North
  • St Lawrence East - Phase 2B; Sidewalk Removals, Watermain Testing, Prep for new Curb & Sidewalk

Monday / Tuesday         

  • Asphalt Removal (Pulverize); St Lawrence East – Wellington to Concession
  • St Lawrence East – Phase 2A, Wellington Intersection

Wednesday – Friday

  • Temporary Water service connections; St Lawrence East – Phase 3A / 3B (Wellington to Concession